June 2026 Quarterly Activities Report
Highlights
PROSPECT HILL TIN PROJECT, SOUTH AUSTRALIA
• Program for environment protection and rehabilitation (PEPR) granted by South Australia’s
Department for Energy and Mining (DEM) in preparation for maiden drilling program at the
South Ridge tin project, Prospect Hill
• Heritage Clearance granted following positive Collaboration with Dieri Aboriginal
Corporation and an anthropologist to conduct a Heritage Survey
• With all approvals in place, drilling contractor based in South Australia has subsequently
been engaged
• Surface geological mapping extends total known outcrop of the main South Ridge Shear
zone to 1.85km, with previously unknown structures identified parallel to shear
• Drilling program increased to up to 38 holes for 3,400m (from 28 drill holes for 2,500m), and
designed to collect material for metallurgical work and maiden MRE
• Camp site finalised and collar pegs set in preparation for upcoming drill program, and
Company now awaiting roads to reopen to heavy vehicle traffic
SUBRON RARE EARTHS PROJECT, WESTERN AUSTRALIA
• Rare Earths expert engaged to conduct strategic review of Subron (formerly ‘Cowalinya’)
Rare Earth project with focus on Heavy Rare Earth Oxides (HREO)
• A combined ~12.9km of high grade HREO mineralised strike and 10 high grade domains have
been identified along newly delineated Structural Corridors within the JORC 159Mt @
870ppm TREO resource1
, with multiple others outside the initial resource area
• Outstanding intercept at newly named Seawolf prospect of 8m @ 3057ppm TREO,
1344ppm HREO average, with a 42% HREO ratio, from 27m (AC360)
• Key drill database metrics to support higher grade TREO & HREO domains include:
o 190 Significant Intercept (SI) drill intervals (>1000ppm TREO),
for an average 1685ppm TREO, with 441ppm HREO for a 25% HREO ratio
o 150 SI drill intervals (>300ppm HREO) for an average 1653ppm TREO, with
579ppm HREO for a 38% HREO ratio
Heavy Rare Earths Limited (“HRE” or “the Company”) is pleased to provide its activities report for
the quarter ending 30 June 2026.
1
Refer to ASX Announcement dated 3 October 2023
Heavy Rare Earths Limited ACN 648 991 039
Level 21, 459 Collins Street, Melbourne VIC 3000 | +61 3 8630 3321 | info@hreltd.com.au | Page 2 of 12 ASX:HRE
Prospect Hill Tin Project: Permits and Clearance in place, Drilling imminent
During the reporting period, the Company submitted a program for environment protection and
rehabilitation (PEPR) to South Australia’s Department for Energy and Mining (DEM) in relation to
HRE’s maiden drilling program at the South Ridge tin project. Post-quarter end, the company
announced that it had successfully received the PEPR from the South Australian DEM for its maiden
drill program.
The Company has been collaborating closely with the Dieri Aboriginal Corporation, the registered
Native Title Body Corporate representing the Dieri People, and received Heritage Clearance from
Dieri during the quarter. This followed a visit to the Prospect Hill Tin Project, attended by HRE’s
Exploration Manager, Joseph Ogierman, an anthropologist and representatives of the Dieri to
complete the survey of the planned drill holes.
Image 1: HRE and members of the Dieri inspecting a proposed drill site
We thank the members of the Dieri and anthropologist for collaborating in what was a constructive
and successful clearance trip. The experience was another example of the respectful and
successful collaboration with the Dieri at Prospect Hill following original clearance for a survey
completed in 2017.
With all permits in place a drilling contractor based in South Australia has been engaged for the drill
program at Prospect Hill. The Company awaits road conditions to improve and re-open to heavy
vehicle traffic to allow mobilisation of earth works and drilling crews.
Heavy Rare Earths Limited ACN 648 991 039
Level 21, 459 Collins Street, Melbourne VIC 3000 | +61 3 8630 3321 | info@hreltd.com.au | Page 3 of 12 ASX:HRE
Prospect Hill Tin Project: Drill Program expanded following ground survey findings
The geological team systematically surveyed western extensions to the South Ridge tin project
making traverses perpendicular to the interpreted strike of the zone. This work showed the South
Ridge Shear zone is up to 10m wide and extends west until it is truncated by another, younger shear
zone (Figure 1). The zone could not be traced beyond this, due to shallow covering of recent
alluvials, so the potential for an offset structure remains. The total mapped outcrop of the main
South Ridge Shear zone now extends for up to 1.85km.
A review of historical data by the company focused on the western portion of the South Ridge Shear
zone and found this section remains under-explored, with only 7 drillholes completed within a 450-
metre strike length (Figure 1). Two of these drillholes intersected high-grade tin mineralisation (see
Havilah Resources ASX:HAV announcement, 1 June 20172
). All seven drillholes were completed by
Havilah Resources over 9 years ago and there has been no follow up drilling.
• PHRC56: 4m @ 1.04%Sn, from 111m
• PHRC59 : 1m @ 1.38%Sn, from 34m
Figure 1. South Ridge Lode showing extensions to main mineralised zone which now measures 1.85km
Geological mapping, in conjunction with pXRF testing, identified several other parallel structures
proximal to South Ridge (Figure 1), which will require further work including potential drill testing.
2
Refer to HAV ASX Announcement dated 1 June 2017
Heavy Rare Earths Limited ACN 648 991 039
Level 21, 459 Collins Street, Melbourne VIC 3000 | +61 3 8630 3321 | info@hreltd.com.au | Page 4 of 12 ASX:HRE
The upcoming program has consequently been increased from 24 drill holes for 2,500m, to up to
38 drill holes for 3,400m providing increased flexibility. The program will comprise of both reverse
circulation and diamond drilling and has been designed to expand the known mineralisation model
and provide material for metallurgical testwork. Camp sites have been selected for drill crews and
geological crews at the base of South Ridge.
Figure 4: Longitudinal view, looking north, of the South Ridge Prospect interpreted mineralisation model, showing zones of
potential mineralisation extension, and drillhole piercement points on surface shown as coloured dots.
As the company approaches its maiden drilling program at South Australia’s largest and most
advanced Tin Project, South Ridge, at Prospect Hill, the results of this detailed surface mapping
program conducted by our field crews are highly encouraging. We now have all approvals for drilling
following the approval of our PEPR, and we look forward to commencing an expanded program as
soon as roads re-open.
HRE acquired a rich historical database that includes historical intersections such as 5m @ 3.22%
Sn and is strongly suggestive strong potential to define high-grade tin deposits. The Company
subsequently negotiated all the mineral rights to Prospect Hill, including the Tin Project (refer to
ASX announcement 28 October 2025).
Based on new and historic data, the Company anticipates the expanded 38-hole drill program may
enable the definition of a maiden resource estimate for a high-grade tin resource at the South Ridge
prospect and looks forward to updating the market as the program advances.
Heavy Rare Earths Limited ACN 648 991 039
Level 21, 459 Collins Street, Melbourne VIC 3000 | +61 3 8630 3321 | info@hreltd.com.au | Page 5 of 12 ASX:HRE
Subron Rare Earths Project, Western Australia
During the quarter the Company commenced a strategic review of its Subron (formerly ‘Cowalinya’)
rare earths project in Western Australia with a focus on HREO3
. The Company’s recently refreshed
board believes that Subron has the potential to generate significant value given its scale, quality,
and location relative to key infrastructure, and intends to leverage its extensive data set to
maximise value for shareholders.
The market has evolved since the project was acquired and drilled, and HRE is particularly
interested in the heavy rare earths, or “heavies”, due to their critical role in defence, the global
energy transition, and the urgent need to secure supply chains outside of China. The upside for our
shareholders and the company is that we already have a significant geological database for
Cowalinya. This comprises over 550 drillholes, with assay, density, weathering, and geology data
ready to be interrogated and reinterpreted. In addition, we have sample material in storage
available for subsequent metallurgical testwork.
Subron rare earth project is located in south-central Western Australia (Figure 4). Tenure is situated
in an area of non-farming, unallocated crown land 110km NNE of the port of Esperance, and well
located logistically, 70kmfrom the Coolgardie-Esperance Highwayand350kmsouth of the recently
constructed Kalgoorlie Rare Earth Processing Facility.
3
Refer to ASX release dated 30th
June 2026
Heavy Rare Earths Limited ACN 648 991 039
Level 21, 459 Collins Street, Melbourne VIC 3000 | +61 3 8630 3321 | info@hreltd.com.au | Page 6 of 12 ASX:HRE
Figure 4: the Location of HRE’s Subron (previously Cowalinya) REE Project is close to Esperance port and the
Kalgoorlie Rare Earth Processing Facility.
The project hosts a JORC inferred resource of 159 million tonne @ 870 ppm TREO (refer ASX release
3 October 2023) with an impressive 28% of TREO made up of the magnetic rare earths (MREOs Pr +
Nd + Tb + Dy).
Table 1: 2023 Mineral Resource Estimate for Cowalinya Rare Earth Project showing individual REOs and
potentially deleterious elements.
Heavy Rare Earths Limited ACN 648 991 039
Level 21, 459 Collins Street, Melbourne VIC 3000 | +61 3 8630 3321 | info@hreltd.com.au | Page 7 of 12 ASX:HRE
An indication of higher-grade domains can be supported by some notable drill-hole intercepts from
HRE’s 2022 drill program4
including:
• 14 metres @ 3,217 ppm TREO (32.5% MREO) from 16 metres (AC225)
o including 6 metres @ 5,848 ppm TREO from 24 metres
• 10 metres @ 2,087 ppm TREO (25.1% MREO) from 17 metres (AC221)
o including 4 metres @ 4,266 ppm TREO from 17 metres
• 8 metres @ 1,175 ppm TREO (24.4% MREO) from 31 metres (AC520)
o including 2 metres @ 3,449 ppm TREO from 31 metres
• 12 metres @ 1,690 ppm TREO (22.7% MREO) from 16 metres (AC487)
o including 2 metres @ 5,192 ppm TREO from 20 metres
Post-quarter end the company announced that the strategic review revealed Subron to be one of
the highest HREO ratio residual clay deposits of its kind5
. This was supported by the drilling data
showing 150 intersections grading above 300ppm HREO with an outstanding 579ppm HREO
average grade and 38% HREO ratio. This has immense value and provides a clear point of difference
from most rare earths projects.
These exceptional high-grade HREO ratio zones may be amenable to concentration and yield a far
higher value proposition for processing. Builds upon the significant amount of work done already,
the Company will conduct further work focused on mineralogy, re-domaining the resource and
metallurgical testwork.
Of strategic interest to the refreshed HRE board are areas of higher grade REE’s that are enriched in
the HREOs (Eu + Gd + Tb + Dy + Ho + Er + Tm + Yb + Lu + Y). A review on this basis of the existing
drilling database comprising 547 aircore (AC) holes completed by the Company (and previous
explorers), successfully identified hundreds of significant intersections that support the presence
of such higher-grade TREO and HREO domains.
For example:
• Applying a >1000ppm TREO cut-off results in:
4
Refer to ASX announcements dated 31st
January 2023, 29th March 2023, 12th April 2023, 1st May
2023, 3rd October 2023
5
Refer to ASX announcement dated 20th
July 2026
Heavy Rare Earths Limited ACN 648 991 039
Level 21, 459 Collins Street, Melbourne VIC 3000 | +61 3 8630 3321 | info@hreltd.com.au | Page 8 of 12 ASX:HRE
o 190 Significant Intercept drill intervals, including:
o 583 individual 1m intervals grading > 1000ppm TREO
o For an average 1685ppm TREO, with 441ppm HREO representing a 25% HREO
ratio
• Applying a >300ppm HREO cut-off results in:
o 150 Significant Intercept drill intervals; including:
o 454 individual 1m intervals grading > 300ppm HREO
o for an average 1653ppm TREO, with 579ppm HREO representing a 38% HREO
ratio
The distribution of the rare earth oxides (REO) within the Subron >300ppm HREO dataset is
presented in the pie chart below. The discovery of this higher grade, higher value composition of
rare earths presents a new value proposition at Subron given the demand, and strategic value of
the heavy rare earth element oxides Yttrium oxide (Y2O3), Terbium oxide (Tb4O7) and Dysprosium
oxide (Dy2O3).
Figure 2. Rare earth oxide distribution with Subron’s >300ppm HREO drilling assays
Heavy Rare Earths Limited ACN 648 991 039
Level 21, 459 Collins Street, Melbourne VIC 3000 | +61 3 8630 3321 | info@hreltd.com.au | Page 9 of 12 ASX:HRE
The Company engaged Rare Earths & Critical Minerals consultant Claudio Sheriff to undertake the
Strategic Review of Subron. 10 HREO high grade domains have been constrained by drill intercepts,
delineated by underlying magnetics and interpreted structural trends. These domains represent a
combined ~12.9km of high grade HREO mineralised strike and bolsters Subron’s potential for a
meaningful resource of higher-grade material. These initial observations will be followed up by re-
domaining the current JORC mineral resource at Subron.
The Seawolf Prospect is a priority target, it has the highest-grade intersections at Subron recording 8m
@ 3057ppm TREO, 1344ppm HREO average, with a 42% HREO ratio. Additional drilling at Seawolf
and otherprospects will be required tobetter define the high-grade mineralisation andconvertInferred
resources to Indicated.
Table 1.Interpreted high grade domainsand significant interceptsat Subron
Corporate
During the quarter, the Company announced the appointment of Mr Jason Barnett as Managing
Director (MD) and Chief Executive Officer (CEO). Mr Barnett is a seasoned mining executive with
over 20 years of experience across critical minerals and gold in Australia and Canada, underpinned
by a strong technical foundation built through operational positions, resource geology consulting,
and project management.
Mr Barnett served as Business Development Manager at Technology Metals Australia (ASX: TMT),
where he played a key role in establishing a downstream processing business for vanadium
electrolyte, as well as driving strategic partnerships and corporate development initiatives for the
company. Mr Barnett has an extensive network in Australia and Canada and a strong understanding
Heavy Rare Earths Limited ACN 648 991 039
Level 21, 459 Collins Street, Melbourne VIC 3000 | +61 3 8630 3321 | info@hreltd.com.au | Page 10 of 12 ASX:HRE
of the development pathway for critical minerals and exploration projects. He holds a degree in
Geology from Macquarie University and an MBA from the University of Western Australia.
Interests in Mining Tenements
Below is a summary of the mining tenements held by the Company at the end of the quarter:
Mining Tenement Location Beneficial
Percentage held
Interest acquired/farm-
in or (disposed)/farm-
out during the quarter
E63/1972 – Cowalinya Project WA, Australia 100% -
E63/2144 – Cowalinya Project WA, Australia 100% -
E70/6397 – Perenjori Project WA, Australia - (100%)
E70/6398 – Perenjori Project WA, Australia - (100%)
E59/2905 – Perenjori Project WA, Australia - (100%)
EL33101 – Duke Project NT, Australia 100% -
EL33194 – Duke Project NT, Australia 100% -
EL 6041 – Radium Hill SA, Australia 80%* -
EL 6594 – Radium Hill SA, Australia 80%* -
EL 5831 – Radium Hill SA, Australia 80%* -
EL 5848 – Lake Namba-Billeroo SA, Australia 80%** -
EL 5785 – Lake Namba-Billeroo SA, Australia 80%** -
EL 5824 – Lake Namba-Billeroo SA, Australia 80%** -
EL 5915 – Lake Namba-Billeroo SA, Australia 80%** -
EL 5940 – Lake Namba-Billeroo SA, Australia 80%** -
EL 6056 – Lake Namba-Billeroo SA, Australia 80%** -
EL 6356 – Lake Namba-Billeroo SA, Australia 80%** -
EL 6358 – Lake Namba-Billeroo SA, Australia 80%** -
EL 6408 – Lake Namba-Billeroo SA, Australia 80%** -
EL 6409 – Lake Namba-Billeroo SA, Australia 80%** -
EL 6410 – Lake Namba-Billeroo SA, Australia 80%** -
EL 6411 – Lake Namba-Billeroo SA, Australia 80%** -
EL 6434 – Lake Namba-Billeroo SA, Australia 80%** -
EL 6546 – Lake Namba-Billeroo SA, Australia 80%** -
EL 6661 – Lake Namba-Billeroo SA, Australia 80%** -
EL 6662 – Lake Namba-Billeroo SA, Australia 80%** -
EL 5891 – Prospect Hill SA, Australia 80%** -
EL 6271 – Prospect Hill SA, Australia 80%** -
EL 6933 – Prospect Hill SA, Australia 80%** -
* U, Sc and REE rights only. Subject to meeting earn-in expenditure obligations.
** U rights only. Subject to meeting earn-in expenditure obligations.
During the quarter the Company relinquished its interest in the Perenjori tenements (E70/6397, E70/6398,
E59/2905).
Appendix 5B related party payments
Amounts included in section 6.1 of the Appendix 5B relate to Director’s fees paid for the June 2026 quarter.
Heavy Rare Earths Limited ACN 648 991 039
Level 21, 459 Collins Street, Melbourne VIC 3000 | +61 3 8630 3321 | info@hreltd.com.au | Page 11 of 12 ASX:HRE
Expenditure during the quarter
Exploration and evaluation expenditure during the quarter totalled $223,000 as disclosed in the accompanying
Appendix 5B,Themajorityof theexpenditure related to geological consulting and labour costs at theRadium Hill
and Lake Namba-Billeroo tenements and tenement maintenance costs.
There were no production activities conducted during the quarter.
This announcement has beenapproved by the Board of HRE
For more information, please contact:
Jason Barnett
CEO MD
+61 03 8630 3321
info@hreltd.com.au
Alex Cowie
NWR Communications
+61 412 952 610
alexc@nwrcommunications.com.au
About Heavy Rare Earths Limited
Heavy Rare Earths Limited (ASX:HRE) is an Australian uranium and critical minerals exploration and development
company. HRE’s key exploration projects are in the uranium-and critical minerals-rich Curnamona Province of eastern
South Australia and in the Mid-West region of Western Australia.
Competent Person’s Statement
The Exploration Results contained in this announcement were compiled by Mr Joseph Ogierman. Mr Ogierman is a
Member (#4469) of the Australian Institute of Geoscientists (MAIG). He is a full-time employee of Heavy Rare Earths
Limited. Mr Ogierman has more than 35 years’ experience in mineral exploration and has sufficient experience relevant
to the style of mineralisation and type of deposit under consideration to qualify as a Competent Person as defined in
the 2012 JORC Code. Mr Ogierman consents to the inclusion in this announcement of the matters based on the
Exploration Results in the form and context in which they appear.
The Exploration Results contained in this announcement relating to the Subron (Cowalinya) Project were compiled by
Mr Claudio Sheriff. Mr Sheriff is a member of the Australasian Institute of Mining and Metallurgy. He is a consultant to
Heavy Rare Earths Limited. Mr Sheriff has more than 20 years’ experience in mineral exploration and has sufficient
experience relevant to the style of mineralisation and type of deposit under consideration to qualify as a Competent
Person as defined in the 2012 JORC Code. Mr Sheriff consents to the inclusion in this announcement of the matters
based on the Exploration Results in the form and context in which they appear.
Compliance Statement
The information in this report that relates to Mineral Resources is extracted from the ASX announcement entitled "FIVE-
FOLD INCREASE IN MINERAL RESOURCES TO 159 Mt @ 870 ppm TOTAL RARE EARTH OXIDES AT COWALINYA
PROJECT IN WESTERN AUSTRALIA" dated 3 October 2023, which is available to view on the ASX website. The Company
confirms that it is not aware of any new information or data that materially affects the information included in the
original market announcement. The Company confirms that the form and context in which the Competent Person’s
findings are presented have not been materially modified from the original market announcement. The Company
confirms that all material assumptions and technical parameters underpinning the estimates in the relevant market
announcement continue to apply and have not materially changed
Heavy Rare Earths Limited ACN 648 991 039
Level 21, 459 Collins Street, Melbourne VIC 3000 | +61 3 8630 3321 | info@hreltd.com.au | Page 12 of 12 ASX:HRE
Forward Looking Statement
This announcement includes “forward-looking statements” as that term within the meaning of securities laws of
applicable jurisdictions. Forward-looking statements involve known and unknown risks, uncertainties and other
factors that are in some cases beyond HRE’s control. These forward-looking statements include, but are not limited to,
all statements other than statements of historical facts contained in this presentation, including, without limitation,
those regarding HRE’s future expectations. Readers can identify forward-looking statements by terminology such as
“aim,” “anticipate,” “assume,” “believe,” “continue,” “could,” “estimate,” “expect,” “forecast,” “intend,” “may,”
“plan,” “potential,” “predict,” “project,” “risk,” “should,” “will” or “would” and other similar expressions. Risks,
uncertainties and other factors may cause HRE’s actual results, performance, production or achievements to differ
materially from those expressed or implied by the forward-looking statements (and from past results, performance or
achievements). Readers are cautioned not to place undue reliance on forward-looking statements. Although HRE
believes that its expectations reflected in these forward-looking statements are reasonable, such statements involve
risks and uncertainties and no assurance can be given that actual results will be consistent with these forward-looking
statements.
Rule 5.5
ASX Listing Rules Appendix 5B (17/07/20) Page 1
+ See chapter 19 of the ASX Listing Rules for defined terms.
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
HEAVY RARE EARTHS LIMITED
ABN Quarter ended (“current quarter”)
35 648 991 039 30 June 2026
Consolidated statement of cash flows Current quarter
$A’000
Year to date
(12 months)
$A’000
1. Cash flows from operating activities
- -
1.1 Receipts from customers
1.2 Payments for
(223) (701)
(a) exploration & evaluation
(b) development - -
(c) production - -
(d) staff costs (58) (145)
(e) administration and corporate costs (178) (625)
1.3 Dividends received (see note 3) - -
1.4 Interest received 8 53
1.5 Interest and other costs of finance paid - -
1.6 Income taxes paid - -
1.7 Government grants and tax incentives - -
1.8 Other (provide details if material) - -
1.9 Net cash from / (used in) operating
activities
(451) (1,418)
2. Cash flows from investing activities
- -
2.1 Payments to acquire or for:
(a) entities
(b) tenements - -
(c) property, plant and equipment - (58)
(d) exploration & evaluation - -
(e) investments - -
(f) other non-current assets - -
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 2
+ See chapter 19 of the ASX Listing Rules for defined terms.
Consolidated statement of cash flows Current quarter
$A’000
Year to date
(12 months)
$A’000
2.2 Proceeds from the disposal of:
- -
(a) entities
(b) tenements - -
(c) property, plant and equipment - -
(d) investments - -
(e) other non-current assets - -
2.3 Cash flows from loans to other entities - -
2.4 Dividends received (see note 3) - -
2.5 Other (provide details if material) - -
2.6 Net cash from / (used in) investing
activities
- (58)
3. Cash flows from financing activities
- -
3.1 Proceeds from issues of equity securities
(excluding convertible debt securities)
3.2 Proceeds from issue of convertible debt
securities
- -
3.3 Proceeds from exercise of options - -
3.4 Transaction costs related to issues of equity
securities or convertible debt securities
- -
3.5 Proceeds from borrowings - -
3.6 Repayment of borrowings - -
3.7 Transaction costs related to loans and
borrowings
- -
3.8 Dividends paid - -
3.9 Other (provide details if material) - -
3.10 Net cash from / (used in) financing
activities
- -
4. Net increase / (decrease) in cash and
cash equivalents for the period
4.1 Cash and cash equivalents at beginning of
period
910 1,935
4.2 Net cash from / (used in) operating
activities (item 1.9 above)
(451) (1,418)
4.3 Net cash from / (used in) investing activities
(item 2.6 above)
- (58)
4.4 Net cash from / (used in) financing activities
(item 3.10 above)
- -
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 3
+ See chapter 19 of the ASX Listing Rules for defined terms.
Consolidated statement of cash flows Current quarter
$A’000
Year to date
(12 months)
$A’000
4.5 Effect of movement in exchange rates on
cash held
- -
4.6 Cash and cash equivalents at end of
period
459 459
5. Reconciliation of cash and cash
equivalents
at the end of the quarter (as shown in the
consolidated statement of cash flows) to the
related items in the accounts
Current quarter
$A’000
Previous quarter
$A’000
5.1 Bank balances 459 910
5.2 Call deposits - -
5.3 Bank overdrafts - -
5.4 Other (provide details) - -
5.5 Cash and cash equivalents at end of
quarter (should equal item 4.6 above)
459 910
6. Payments to related parties of the entity and their
associates
Current quarter
$A'000
6.1 Aggregate amount of payments to related parties and their
associates included in item 1
73
6.2 Aggregate amount of payments to related parties and their
associates included in item 2
-
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a description of, and an
explanation for, such payments.
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 4
+ See chapter 19 of the ASX Listing Rules for defined terms.
7. Financing facilities
Note: the term “facility’ includes all forms of financing
arrangements available to the entity.
Add notes as necessary for an understanding of the
sources of finance available to the entity.
Total facility
amount at quarter
end
$A’000
Amount drawn at
quarter end
$A’000
7.1 Loan facilities - -
7.2 Credit standby arrangements - -
7.3 Other (please specify) - -
7.4 Total financing facilities - -
7.5 Unused financing facilities available at quarter end -
7.6 Include in the box below a description of each facility above, including the lender, interest
rate, maturity date and whether it is secured or unsecured. If any additional financing
facilities have been entered into or are proposed to be entered into after quarter end,
include a note providing details of those facilities as well.
N/A
8. Estimated cash available for future operating activities $A’000
8.1 Net cash from / (used in) operating activities (item 1.9) (451)
8.2 (Payments for exploration & evaluation classified as investing
activities) (item 2.1(d))
-
8.3 Total relevant outgoings (item 8.1 + item 8.2) (451)
8.4 Cash and cash equivalents at quarter end (item 4.6) 459
8.5 Unused finance facilities available at quarter end (item 7.5) -
8.6 Total available funding (item 8.4 + item 8.5) 459
8.7 Estimated quarters of funding available (item 8.6 divided by
item 8.3)
1.02
Note: if the entity has reported positive relevant outgoings (ie a net cash inflow) in item 8.3, answer item 8.7 as “N/A”.
Otherwise, a figure for the estimated quarters of funding available must be included in item 8.7.
8.8 If item 8.7 is less than 2 quarters, please provide answers to the following questions:
8.8.1 Does the entity expect that it will continue to have the current level of net operating
cash flows for the time being and, if not, why not?
Answer: Yes, the Company expects to progress with its drilling activities and further
exploration activities as announced recently.
8.8.2 Has the entity taken any steps, or does it propose to take any steps, to raise further
cash to fund its operations and, if so, what are those steps and how likely does it
believe that they will be successful?
Answer: Yes, the Company continually reviews its funding requirements and is actively
engaged in discussions with potential financiers.
8.8.3 Does the entity expect to be able to continue its operations and to meet its business
objectives and, if so, on what basis?
Answer: Refer to response above for section 8.8.2.
Note: where item 8.7 is less than 2 quarters, all of questions 8.8.1, 8.8.2 and 8.8.3 above must be answered.
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 5
+ See chapter 19 of the ASX Listing Rules for defined terms.
Compliance statement
1 This statement has been prepared in accordance with accounting standards and policies which
comply with Listing Rule 19.11A.
2 This statement gives a true and fair view of the matters disclosed.
Date: 31 July 2026
Authorised by: The Board of Directors
Notes
1. This quarterly cash flow report and the accompanying activity report provide a basis for informing the market about the
entity’s activities for the past quarter, how they have been financed and the effect this has had on its cash position. An
entity that wishes to disclose additional information over and above the minimum required under the Listing Rules is
encouraged to do so.
2. If this quarterly cash flow report has been prepared in accordance with Australian Accounting Standards, the definitions
in, and provision
Share your feedback
Discover